SPARK, Walsall - Project Update

April 2, 2025

Amazing progress in just two weeks at Project SPARK - Walsall

Unit A - 90% of Foundations installed, Dock Leveller being shuttered and poured, 15m x 3mØ Separator in the ground.

Unit G - Outfall drainage connections through live service yard next week.

A perfect example of what can be achieved by Hannon Brothers with good weather & a clear site.

https://youtu.be/mActo135ijU

Molson Coors - Project Update

March 7, 2025

Final touches are being completed at Molson Coors new offices in Burton, ready for practical completion handover on Monday.

Refurbishment and extension of the former National Brewery Centre into Molson Coors new headquarters.

Our works included the replacement of existing and new drainage, ducting, floor slab renewal, internal drainage connections, new paving, street furniture supply & install, remedial works to the car park including replacing the defective sub base, tarmac road base and binder.

We think it looks great and will hopefully be enjoyed by employees & guests for years to come.

www.bhbarchitects.co.uk/our-projects/masterplanning/molson-coors-head-office

Infinity Park - Project Update

February 28, 2025

It's great to see the final results of everyones hard work at Plot D2, Infinity park, Derby.

Works included a 507,000 sq ft unit, 16,000m2 service yard, permeable parking bays, 24nr headwalls of various sizes with some including automated penstocks, gabion walls & the civils associated with an adoptable section of a proposed new link road.

The new link road is planned to connect Infinity Park to a dedicated junction on the A50, works on progressing the link road are due to commence in 2026.

The project achieved EPC 'A+' and BREEAM ‘Excellent’ rating and was completed on time & budget for our valued client Bowmer + Kirkland.

https://infinityparkderby.co.uk/

New job award - Project Spark, Walsall

February 17, 2025

Hannon Brothers are delighted to have been chosen by their valued repeat client Bowmer + Kirkland to undertake the groundworks for a new commercial logistics development at Project Spark, Walsall.

Following remediation of 1.3m tonnes of soil & the crushing of 150,000 Tonnes of concrete for re-use, Hannon Brothers are looking to start works in Feburary 2025 to provide the first two units on this site.

https://hbd.co.uk/scheme/spark/

TASK - Project Update

January 30, 2025

Despite the wet weather, Phase 1 handover of the concrete circulation road is still on target.

This will enable the possession of the current access route for the building platform preparation, bases to be dug & the steel frame to be erected.

We are making good use of time on site without other frame contractors to get as much of the external yard installed in advance, providing a safe laydown and access routes to follow on trades.

New job award - Bentley, Crewe

November 20, 2024

Hannon Brothers have been chosen by their valued repeat client McLaren Construction Group to undertake the groundworks for the prestigious Bentley Motor Company and the new Integrated Logistics Centre in Crewe.

Following Demolition of the 86,000 sq ft temporary logistics centre at its Pyms Lane campus, a new 145,000 sq ft permanent facility will be erected in its place.

Works planned to commence in earnest, January 2025.

https://www.cheshire-live.co.uk/news/chester-cheshire-news/bentleys-switch-electric-gathers-speed-27936748

TASK - Project Update

November 13, 2024

Works progressing well at TASK Wolverhampton Keeping the pressure on to get the new circulation road down before removing the old access and maintaining 24/7 production to existing facility throughout the build.

New job award - Home Bargains Distribution Centre, adaptions

October 28, 2024

Working direct for TJ Morris

Works to involve alterations to a newly constructed distribution warehouse in Warrington.

Formation of a RC pit within the existing building to house automation equipment controlling the goods in and out process, as well as installing 4no. external concrete plinths to cater for back-up generators.

Works commenced October 2024 with completion by year end.

New job award - TASK Wolverhampton

October 16, 2024

We are delighted to be awarded the Groundworks package for TASK in Wolverhampton for our repeat client Benniman Construction Group.

The works will comprise of an extension to existing live manufacturing facilities as well as an additional stand-alone warehouse & office building.

Task Consumer Products: 50 new jobs in £30m expansion of firm - BBC News

New job award - Washwood Heath

September 23, 2024

We are happy to add a new client to our roster, having secured Washwood Heath for Glencar Construction.

The development will be in place of the old LDV van manufacturing facility and will consist of 4nr new industrial units, associated service yards & access road.

New plans for industrial units next to Birmingham HS2 depot - Business Live (business-live.co.uk)

Infinity Park - Kerb Extruder

August 29, 2024

As part of our drive to always improve our practices and generate greater efficiencies, when we were required to install a kerb brace for the S38 works at Infinity Park Derby to adoptable standards, rather than utilising traditional road-forms we were able to let the works to PDK Kerb Extrusion. Working with our machine in attendance we were able to vastly improve on our expected outputs & improve on a tight programme.

Featured blog.

SPARK, Walsall - Project Update

Amazing progress in just two weeks at Project SPARK - Walsall

Unit A - 90% of Foundations installed, Dock Leveller being shuttered and poured, 15m x 3mØ Separator in the ground.

Unit G - Outfall drainage connections through live service yard next week.

A perfect example of what can be achieved by Hannon Brothers with good weather & a clear site.

https://youtu.be/mActo135ijU

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.
April 2, 2025

SPARK, Walsall - Project Update

Amazing progress in just two weeks at Project SPARK - Walsall

Unit A - 90% of Foundations installed, Dock Leveller being shuttered and poured, 15m x 3mØ Separator in the ground.

Unit G - Outfall drainage connections through live service yard next week.

A perfect example of what can be achieved by Hannon Brothers with good weather & a clear site.

https://youtu.be/mActo135ijU

March 7, 2025

Molson Coors - Project Update

Final touches are being completed at Molson Coors new offices in Burton, ready for practical completion handover on Monday.

Refurbishment and extension of the former National Brewery Centre into Molson Coors new headquarters.

Our works included the replacement of existing and new drainage, ducting, floor slab renewal, internal drainage connections, new paving, street furniture supply & install, remedial works to the car park including replacing the defective sub base, tarmac road base and binder.

We think it looks great and will hopefully be enjoyed by employees & guests for years to come.

www.bhbarchitects.co.uk/our-projects/masterplanning/molson-coors-head-office

February 28, 2025

Infinity Park - Project Update

It's great to see the final results of everyones hard work at Plot D2, Infinity park, Derby.

Works included a 507,000 sq ft unit, 16,000m2 service yard, permeable parking bays, 24nr headwalls of various sizes with some including automated penstocks, gabion walls & the civils associated with an adoptable section of a proposed new link road.

The new link road is planned to connect Infinity Park to a dedicated junction on the A50, works on progressing the link road are due to commence in 2026.

The project achieved EPC 'A+' and BREEAM ‘Excellent’ rating and was completed on time & budget for our valued client Bowmer + Kirkland.

https://infinityparkderby.co.uk/

February 17, 2025

New job award - Project Spark, Walsall

Hannon Brothers are delighted to have been chosen by their valued repeat client Bowmer + Kirkland to undertake the groundworks for a new commercial logistics development at Project Spark, Walsall.

Following remediation of 1.3m tonnes of soil & the crushing of 150,000 Tonnes of concrete for re-use, Hannon Brothers are looking to start works in Feburary 2025 to provide the first two units on this site.

https://hbd.co.uk/scheme/spark/

January 30, 2025

TASK - Project Update

Despite the wet weather, Phase 1 handover of the concrete circulation road is still on target.

This will enable the possession of the current access route for the building platform preparation, bases to be dug & the steel frame to be erected.

We are making good use of time on site without other frame contractors to get as much of the external yard installed in advance, providing a safe laydown and access routes to follow on trades.

November 20, 2024

New job award - Bentley, Crewe

Hannon Brothers have been chosen by their valued repeat client McLaren Construction Group to undertake the groundworks for the prestigious Bentley Motor Company and the new Integrated Logistics Centre in Crewe.

Following Demolition of the 86,000 sq ft temporary logistics centre at its Pyms Lane campus, a new 145,000 sq ft permanent facility will be erected in its place.

Works planned to commence in earnest, January 2025.

https://www.cheshire-live.co.uk/news/chester-cheshire-news/bentleys-switch-electric-gathers-speed-27936748

November 13, 2024

TASK - Project Update

Works progressing well at TASK Wolverhampton Keeping the pressure on to get the new circulation road down before removing the old access and maintaining 24/7 production to existing facility throughout the build.

October 28, 2024

New job award - Home Bargains Distribution Centre, adaptions

Working direct for TJ Morris

Works to involve alterations to a newly constructed distribution warehouse in Warrington.

Formation of a RC pit within the existing building to house automation equipment controlling the goods in and out process, as well as installing 4no. external concrete plinths to cater for back-up generators.

Works commenced October 2024 with completion by year end.

October 16, 2024

New job award - TASK Wolverhampton

We are delighted to be awarded the Groundworks package for TASK in Wolverhampton for our repeat client Benniman Construction Group.

The works will comprise of an extension to existing live manufacturing facilities as well as an additional stand-alone warehouse & office building.

Task Consumer Products: 50 new jobs in £30m expansion of firm - BBC News

September 23, 2024

New job award - Washwood Heath

We are happy to add a new client to our roster, having secured Washwood Heath for Glencar Construction.

The development will be in place of the old LDV van manufacturing facility and will consist of 4nr new industrial units, associated service yards & access road.

New plans for industrial units next to Birmingham HS2 depot - Business Live (business-live.co.uk)

August 29, 2024

Infinity Park - Kerb Extruder

As part of our drive to always improve our practices and generate greater efficiencies, when we were required to install a kerb brace for the S38 works at Infinity Park Derby to adoptable standards, rather than utilising traditional road-forms we were able to let the works to PDK Kerb Extrusion. Working with our machine in attendance we were able to vastly improve on our expected outputs & improve on a tight programme.