New warehouse acquisition, the new owner required adjustments to suit their revised production needs.
Removed slab and installed mezzanine deck foundations, weighbridge ramps and foundations including new gatehouse. Additional external drainage and yard reinstatement together with the installation of new sprinkler ring main, sprinkler tank and condenser bases.
Extension, & new Warehouse to an existing processing facility for TASK consumer products.
Construction of the Integrated Logistics Centre, for the Luxury Car Manufacturer Bentley
Construction of a 500,000sqft warehouse & adoptable road, for future connection to a new A50 junction.
Demolition of an existing 1,000,000 sqft warehouse & re-development into three smaller units.
Initially undertaking the enabling works including the main access spine road, services, drainage, headwalls and Tarmac. Hannon Brothers were awarded the main works which consisted of the construction of 4nr new units over 2 sites.