McLaren Construction Group

Warrington - Omega Park Phase II

Industrial
Warehousing

35 wks

-

Duration

£5.7m

-

Order Value

Warrington

-

Location

McLaren Construction Group

Client

Project Details

Mountpark Warrington Omega II is a development at the gateway to Omega South comprising three units totalling 736,884 sq ft.

Initially Hannon brothers were contracted to complete two of the three units. However, due to the developer securing a tenant to one of the units mid-build and their confidence in our ability to deliver, we were awarded an additional unit to complete. This involved re-sequencing and re-planning our works to involve adaptions to the existing unit, to ensure compatibility with incoming tenant requirements including machine plinths and internal conveyor troughs etc. Additional notable works undertaken involved diversion of a live rising main from the adjacent Dominos production unit, completing SW and FW pumping stations to an adoptable standard for the client, swale diversion and a radiused fair face RC wall to the entrance of the estate.

Related Media

Case study

TASK - Wolverhampton

Extension, & new Warehouse to an existing processing facility for TASK consumer products.

View Full Case Study

Case study

Bentley - Crewe

Construction of the Integrated Logistics Centre, for the Luxury Car Manufacturer Bentley

View Full Case Study

Case study

Infinity Park - Unit D2

Construction of a 500,000sqft warehouse & adoptable road, for future connection to a new A50 junction.

View Full Case Study

Case study

Project Bigfoot - Daventry

Demolition of an existing 1,000,000 sqft warehouse & re-development into three smaller units.

View Full Case Study

Case study

Ansty - Project Holst

Initially undertaking the enabling works including the main access spine road, services, drainage, headwalls and Tarmac. Hannon Brothers were awarded the main works which consisted of the construction of 4nr new units over 2 sites.

View Full Case Study