McLaren Construction Group

Stafford - Pets at Home, Drainage Upgrade

Specialist
Infrastructure & Enabling

4 wks

-

Duration

£0.25m

-

Order Value

Stafford

-

Location

McLaren Construction Group

Client

Project Details

New drainage FW outfall and installation 4m deep Weholite storage tank.

Due to issues with discharge capacity, this involved trenching though an adopted footpath and liaising with the council to ensure the reinstatement was approved.

Related Media

Case study

TASK - Wolverhampton

Extension, & new Warehouse to an existing processing facility for TASK consumer products.

View Full Case Study

Case study

Bentley - Crewe

Construction of the Integrated Logistics Centre, for the Luxury Car Manufacturer Bentley

View Full Case Study

Case study

Infinity Park - Unit D2

Construction of a 500,000sqft warehouse & adoptable road, for future connection to a new A50 junction.

View Full Case Study

Case study

Project Bigfoot - Daventry

Demolition of an existing 1,000,000 sqft warehouse & re-development into three smaller units.

View Full Case Study

Case study

Ansty - Project Holst

Initially undertaking the enabling works including the main access spine road, services, drainage, headwalls and Tarmac. Hannon Brothers were awarded the main works which consisted of the construction of 4nr new units over 2 sites.

View Full Case Study