McLaren Construction Group

Stafford - Pets at Home, Drainage Upgrade

Specialist
Infrastructure & Enabling

4 wks

-

Duration

£0.25m

-

Order Value

Stafford

-

Location

McLaren Construction Group

Client

Project Details

New drainage FW outfall and installation 4m deep Weholite storage tank.

Due to issues with discharge capacity, this involved trenching though an adopted footpath and liaising with the council to ensure the reinstatement was approved.

Related Media

Case study

Ansty - Project Holst

Initially undertaking the enabling works including the main access spine road, services, drainage, headwalls and Tarmac. Hannon Brothers were awarded the main works which consisted of the construction of 4nr new units over 2 sites.

View Full Case Study

Case study

Derby - EMDC

Creation of a new unit built over previous cooling tower foundations and RC Culvert taking water from the adjacent River Trent. The new plot is now adjacent to a busy road and rail freight terminal.

View Full Case Study

Case study

Nottingham - Power Park

Creation of 6nr new units and associated access roads/ car parks on an old landfill tip that previously housed the old Imperial Tabacco factory.

View Full Case Study

Case study

Gloucester - Centre 7 Amazon Unit

One of the first fully EV future-proofed projects we undertook. The job required careful planning to maintain full use of a pedestrian and cycle path through the project.

View Full Case Study

Case study

Redditch - Amazon Gateway

Amazon super-depot distribution facility

View Full Case Study