Clegg Foods

Coventry - Sherbourne Recycling MRF

Specialist
Public Sector

42 wks

-

Duration

£6.85m

-

Order Value

Coventry

-

Location

Clegg Foods

Client

Project Details

A state-of-the-art material recycling facility for Coventry & six other county councils, involving a huge amount of insitu Reinforced Concrete Works.

A challenging project accessed through Coventry Council’s existing yard which only allowed for sectional access around council vehicle parking to enable outfall connections at the start of the job. This site was re-profiled and 8m earth retaining walls were added along one side. The attenuation was dug to utilise as fill and then installed under the future yard. Piled foundations allowed us to complete the cropping and installation of pile caps and drainage, encountering rock on excavation in some areas that was broken out and removed from site. Due to the building’s future purpose (a material recycling facility), there were 670m of 400mm wide 5.25m high in-situ RC walls for material segregation bays to form. Some of the walls had to be formed once the steel structure was erected due to interfaces with the structure which made installing formwork difficult requiring spider cranes in some instances. A complicated automated penstock drainage system with holding tanks was incorporated to prevent discharge of contaminated fire water into the drainage system in the event of a fire. Concrete service yards with inbuilt RC crash barriers were formed as well as machine bases, sprinkler tank bases, pedestrian ramps, in-situ retaining walls, gatehouse and weighbridge formation. To add to the complexity of this job, sectional completion was required for the AI controlled Machinex Fit out with a minimum laydown area on a tight deadline. Through hard work and determination we were successful in achieving this for our client.

Related Media

Case study

TASK - Wolverhampton

Extension, & new Warehouse to an existing processing facility for TASK consumer products.

View Full Case Study

Case study

Bentley - Crewe

Construction of the Integrated Logistics Centre, for the Luxury Car Manufacturer Bentley

View Full Case Study

Case study

Infinity Park - Unit D2

Construction of a 500,000sqft warehouse & adoptable road, for future connection to a new A50 junction.

View Full Case Study

Case study

Project Bigfoot - Daventry

Demolition of an existing 1,000,000 sqft warehouse & re-development into three smaller units.

View Full Case Study

Case study

Ansty - Project Holst

Initially undertaking the enabling works including the main access spine road, services, drainage, headwalls and Tarmac. Hannon Brothers were awarded the main works which consisted of the construction of 4nr new units over 2 sites.

View Full Case Study